試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(7)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(7)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Your project for the U.S. Department of Energy is using earned value analysis as a performance reporting technique. Your project is 201% complete. Results from a recent earned value analysis indicate that the CPI is 0 .67 and the SPI is 0.87. In this situation, you should:
A、Perform additional resource planning, add resources, and use overtime as needed to accomplish the same amount of budgeted work
B、Rebaseline the schedule, then use Monte Carlo analysis
C、Conduct a risk response audit to help control risk
D、Update to Identify Risks, Perform Qualitative Analysis and Perform Quantitative Analysis