試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(6)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(6)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

our management has decided that all orders will be treated as "projects" and that project managers will be used to update orders daily, resolving issues and ensuring that the customer formally accepts the product within 30 days of completion. Revenue from the individual orders can vary from U.S. $100 to U.S. $15O,OOO. The project manager will not be required to perform planning or provide documentation other than daily status. How would you define this situation?
A、Because each individual order is a "temporary endeavor," each order is a project.
B、This is program management since there are multiple projects involved.
C、This is a recurring process
D、Orders incurring revenue over $100,000 would be considered projects and would involve project management