抗美援朝 电视剧在线观看|av国产japan在线播放|91色欧美|复仇岛电影在线观看免费完整版,欧美日韩亚洲一,黑暗迷宫电影在线观看完整版,久久动漫精品

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project team has just completed the development of a new order tracking system. The project sponsor, the director of sales, is pleased with the new system. However, the director of manufacturing is not pleased and has demanded that the system be re-designed to meet manufacturing concerns. The project manager estimates that a system redesign will delay implementation by two months.How could the project manager have avoided this situation?
A、Completed a roles and responsibility matrix in the planning phrase.
B、Involved key stakeholders to ensure that requirements were not overlooked.
C、Ensured that the director of sales had approved the requirements.
D、Developed an effective project scope and change control process during project planning.


相關(guān)試題

推薦文章