抗美援朝 电视剧在线观看|av国产japan在线播放|91色欧美|复仇岛电影在线观看免费完整版,欧美日韩亚洲一,黑暗迷宫电影在线观看完整版,久久动漫精品

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(2)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Jake has been assigned the position of PM of a multi-organizational project. His organization, which is the primary performing organization, has a weak quality policy. The other organizations have no quality policy, Jake should
A、Use the policy for his organization, since his organization is the primary performing organization
B、Ask for additional money from the stakeholders to fund a quality program
C、Seek buy-in from all organizations to fund a quality program
D、Work with the team members from the various organizations and develop a quality policy for the project without telling anyone, to eliminate negative feed back


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容