抗美援朝 电视剧在线观看|av国产japan在线播放|91色欧美|复仇岛电影在线观看免费完整版,欧美日韩亚洲一,黑暗迷宫电影在线观看完整版,久久动漫精品

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(2)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

A client requests a scope change request after accepting the design. This change will have a potential impact on several project components. What is the project manager’s MOST APPROPRIATE response?
A、Convince client to delay change
B、Analysis infects of schedule and cost due to the change, and have meeting with team members
C、If this change is critical, then implement it and inform the CCB
D、Estimate the cost and schedule affected by the change, get approval before implement


相關試題

推薦文章