抗美援朝 电视剧在线观看|av国产japan在线播放|91色欧美|复仇岛电影在线观看免费完整版,欧美日韩亚洲一,黑暗迷宫电影在线观看完整版,久久动漫精品

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(2)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

During the project execution phase, the project manager realizes that a task on the critical path is delayed. The project manager decides to fast track the critical path activities. What is likely to be the impact of this decision on the project?
A、The project will be on schedule but cost and risk will be higher.
B、The project will be within the budget but time and risk will be higher.
C、The project will have less risk but cost and time will be higher.
D、The project will be on schedule and within budget but risk will be higher.


相關試題

推薦文章